New Generator

New Generator

Project Manager

Water Utilities Engineering / Candy Staring, P.E.

SUA Project No. 16WG08


What We're Doing

The City of Stillwater and the Stillwater Utilities Authority will be acquiring a new generator for the Water Treatment Plant (WTP).


Benefits

A new generator will provide back-up power during an electrical outage, and will increase the reliability of the WTP.


How We're Paying For It

Funds to purchase the generator will come from the City's Water Capital Fund. Staff have also applied for a grant through the Oklahoma Department of Emergency Management (OEM). If the grant is awarded, a reimbursement of approximately $2 million will be provided by OEM and FEMA.


Timeline


Updates

February 7, 2017: Black and Veatch hired to provide conceptual design services.

November 8, 2018: The OEM/FEMA grant application was submitted.

December 11, 2018: Conducted the 65% Design Workshop with the Project Team.

January 16, 2019: The Project Team responded to two Requests for Information from OEM/FEMA to support the grant application.


Actions Authorized by Stillwater Utilities Authority (SUA)

  • 1.9.17  I  SUA-17-01  I  Professional Services Agreement

  • 7.17.17  I  SUA-17-22  I  Amendment to Professional Services Agreement

  • 7.23.18  I  CC-18-90  I  Authorization to apply for an Oklahoma Department of Emergency Management (OEM) grant

  • 9.10.18  I  SUA-18-34  I  Request for Additional Expenditures and to Execute Contract Amendments to the Professional Services Agreement

  • 10.15.18  I  CC-18-118 I  Authorization to apply for an Oklahoma Department of Emergency Management (OEM) grant