Country Club Road & 37th Looping

Country Club Road & 37th Looping

Project Manager

Water Resources / Peter Armans

SUA Project No. 12WG17


What We're Doing

We are adding connecting a dead end water line on Country Club Road to the water line at the intersection north on 37th Avenue. Phase 1 of the project was completed in the fall of 2016 and consisted of 750 feet of new water line. Phase 2 will consist of 640 feet of new water line. 


Project Benefits

This project eliminates two dead end lines in the southwest part of Stillwater. This increase in water circulation will improve water quality and increase reliability for the area.


Latest Project Update

September 21, 2017: Phase 2 is currently in design.


Project Timeline

April 26, 2016: Design for Phase 1 is complete.  

July 26, 2016: The notice to proceed for the contractor, Patriot Construction Services, was issued for an Aug. 1, 2016 construction start date.

September 9, 2016: Contractor has completed Phase 1.


Image:

(Click map to enlarge)

map of completed phase 1 and what needs to be done for phase 2

Design for Country Club Water Looping map