Sewer Point Repairs

Sewer Point Repairs

Project Manager

Water Resources / Candy Staring, P.E.

SUA Project No. 15SG02


What We're Doing

The City of Stillwater and Stillwater Utilities Authority is repairing sections of a problematic sewer line in the Summerlin Addition and Village Court areas. 


Project Benefits

The City's Field Services crews make repairs to the sewer system and conduct ongoing maintenance throughout the year. Some repairs require equipment or resources that city crews do not have, which is the case with this sewer point repairs project.


Latest Project UpdateLatest Project Update Timeline

December 14, 2016: Right of Entry and Temporary Construction Easement requests were extended to affected property owners. Once coordination is complete, the next step will be to advertise for bids.


Project Timeline

July 26, 2016: Design is in progress and coordination with affected residents is being planned.


Images:

Summerlin Addition

Aerial map of sewer point repairs in the Summerlin Addition

Village Court (click map to enlarge)

Aerial map of sewer point repairs in Village Court.