Western Road & 32nd Avenue Water Line

Western Road from 44th Ave to Sangre Road & 32nd Avenue Water Line

Project Manager: David Barth, P.E. | Water Resources

SUA Project No. 15WC04, Water 2040


What We're Doing

The two miles of water line will improve service and reliability to the Deer Crossing and Woodland Trails developments and other neighborhoods along the alignment.


Benefits

This project is part of the Water 2040 Program. Click here for more information.


Timeline


Updates

July 7, 2017: Bid opening scheduled for Wednesday, Aug. 9 at 3 p.m. 

August 10, 2017: Bid opening occurred at 3 p.m. Wednesday, August 9, 2017. 

October 13, 2017: Contract awarded to McKee Utility Contractors, Inc.

November 15, 2017: Pre-construction meeting held on October 17th. Notice to Proceed was issued on October 30th.

February 27, 2018: Work notifications have been mailed to residents. Contractor is currently mobilizing on-site and establishing erosion control.

April 5, 2018: Installation of the water line is progressing.

View of excavation trench with installation of water line, valves and valve vault

July 13, 2018: Installation of the water line along Western and 32nd is complete. Contractor is currently disinfecting the new line and will tie-into the existing water line end of July.

October 11, 2018: Water line work is progressing. The Contractor is scheduled to be completed by early November 2018.


Actions authorized by Stillwater Utilities Authority (SUA):