32nd Ave. Booster Pump Station & Water Line

32nd Avenue Booster Pump Station & 6th Avenue to 32nd Avenue Water Line

Formerly titled 32nd Avenue Booster Pump Station

Project Manager: David Barth, P.E. | Water Utilities Engineering

SUA Project No. 15WC06, Water 2040

Visit the GIS Infrastructure Map to see where city infrastructure projects are happening.


What We're Doing

This project includes construction of a new booster pump station (BPS) and installation of three miles of water line connecting the Central Zone at 6th Avenue to the 56th Tower Zone at 32nd Avenue.


Anticipated Milestones

  • Anticipated Date (Design): Design completed April 2019
  • Anticipated Date (Construction): Construction began July 2019
  • Anticipated Date (Completion): November 2020

Benefits of the Project

This connection is required to improve water service and reliability to customers in both pressure zones.


Budget & Funding

  • Year Funded: FY2016
  • Funding Source: Water Fund and Loans
  • Project Budget: $8.1 Million
  • Expenditures to date: $6.1 Million

Project Management


Updates

July 13, 2017: Design process is nearly complete.

February 27, 2018: Easements are currently being finalized and bid package is nearly complete.

April 12, 2018: Awaiting final easement acquisition to advertise for construction bids. 

March 29, 2019: Project Engineer is currently finalizing plans and specifications. Bid advertisement is scheduled for April 2019.

June 3, 2019: Contract awarded to BRB Contractors, Inc.

July 8, 2019: Notice to Proceed issued to BRB Contractors, Inc.

January 23, 2020: BRB has installed 3,000 feet of 18-inch water line. The block walls of the BPS are nearly complete and the roof truss installation will begin soon.

April 23, 2020: BRB has installed approximately 9,000 feet of 18-inch water line. The walls, roofing, and electrical work are in progress at the booster pump station. 

May 29, 2020: BRB has installed approximately 10,000 feet of 18-inch water line, including a critical tie-in at HWY 51 and Pioneer Road. 

June 24, 2020: BRB has installed approximately 12,000 feet of 18-inch water line and interior pumps and pipes in the Booster Pump Station.

July 29, 2020: Water line is being pressure tested and disinfected. Electrical components are currently being installed at the Booster Pump Station. 

November 11, 2020: Water line construction is now complete. Site work and pump testing is progressing within the Booster Pump Station.

January 4, 2021: Testing of the Booster Pump Station is complete and the new water line is now connected to the City's distribution system. BRB is currently completing final restoration.


Actions authorized by Stillwater Utilities Authority (SUA):

  • 12.5.16  l SUA-16-55   l  Real Estate and Easement Acquisition

  • 06.3.19  l SUA-19-23   l  Construction Bid Awarded


Image(s)