19th Ave. Booster Pump Station & Water Line to 44th Tower

19th Ave. Booster Pump Station & Water Line to 44th Tower

Formerly titled Range Road Booster Pump Station & Water Line

Project Manager: Eric Fladie | Water Resources

SUA Project No. 15WC03, Water 2040


What We're Doing

The City of Stillwater and Stillwater Utilities Authority will install 2.5 miles of transmission water line from the future Range Road Booster Pump Station (BPS) on 19th Avenue to the new 44th Tower.


Project Benefits

This project is part of the Water2040 Program. Click here for more information.


Latest Project Update

February 27, 2018: Pump Station slab is complete. Contractors continue to work on site utilities and the water line down Range Road. 

View looking east at the completed foundation for the booster pump station


Project Timeline

June 15, 2017: Pre-bid meeting was held June 1, 2017. Bids are due Wednesday, June 21, 2017.

July 24, 2017: Bids were opened on June 28th and the project will be awarded on August 7th.

August 10, 2017: Wynn Construction Co., Inc. was awarded the construction contract.

October 13, 2017: Construction of the Pump Station foundation is underway.view of tiered excavation for the 19th BPS foundation

Sept. 2017: Post card construction notice sent in September to residences within the area that will be impacted by work.

    


Actions authorized by Stillwater Utilities Authority (SUA):

  • 10.19.15  | SUA-15-52 |  Real Estate Authorization

  • 6.5.17  | CC-17-85 |  Acceptance of Easements

  • 8.7.17  | SUA-17-25 |  Construction Award


Images

Construction update as of 3/13/2018:

Range road bps