19th Ave. Booster Pump Station & Water Line to 44th Tower

 

19th Ave. Booster Pump Station & Water Line to 44th Tower

Formerly Range Road Booster Pump Station & Water Line

Project Manager

Water Resources / Eric Fladie

SUA Project No. 15WC03, Water 2040


What We're Doing

The City of Stillwater and Stillwater Utilities Authority will install 2.5 miles of transmission water line from the future Range Road Booster Pump Station (BPS) on 19th Avenue to the new 44th Tower.


Project Benefits

This project is part of the Water2040 Program. Click here for more information.


Latest Project Update

October 13, 2017: Construction of the Pump Station foundation is underway.view of tiered excavation for the 19th BPS foundation


Project Timeline

June 15, 2017: Pre-bid meeting was held June 1, 2017. Bids are due Wednesday, June 21, 2017.

July 24, 2017: Bids were opened on June 28th and the project will be awarded on August 7th.

August 10, 2017: Wynn Construction Co., Inc. was awarded the construction contract.



Actions authorized by Stillwater Utilities Authority (SUA):

  • 10.19.15  | SUA-15-52 |  Real Estate Authorization

  • 6.5.17  | CC-17-85 |  Acceptance of Easements

  • 8.7.17  | SUA-17-25 |  Construction Award


Images