Bill Millis / Deputy Director / City Engineering
Visit the Stillwater Infrastructure Map to see where city infrastructure projects are happening.
The City is microsurfacing several streets as part of the FY20 Pavement Management Program
Anticipated Date (Design): 2.2021
Anticipated Date (Construction): 9.2021
Anticipated Date (Completion): 10.2021
Microsurfacing is a cost-effective method to renew the road surface and seal minor cracks and other irregularities with a thin, tough layer of asphalt emulsion blended with finely crushed stone for traction. This protective seal coat extends the life of the pavement and improves the ride until resurfacing or reconstruction becomes necessary. Roadways selected for microsurfacing treatment are commonly those which have slight to moderate distress, no rutting, and generally narrow crack widths.
Year Funded: FY2020
Funding Source: Transportation Sales Tax Fund
Project Budget:
Estimated at $234,000
Expenditure to date: $0
08.05.2019: City Council | Approval of FY20/21 Pavement Maintenance Program
Content Last Reviewed: 02.05.2021
![]() |