Bill Millis / Deputy Director / City Engineering
Visit the Stillwater Infrastructure Map to see where City infrastructure projects are happening.
High-Density Mineral Bond or HA5® was developed to meet the demand for effective asphalt preservation on residential roadways without the negative side effects of chip seals or slurry seals. Specifically engineered to preserve the native asphalt binder, HA5 is exceptional at preventing oxidative damage and is designed specifically for residential streets that are still in good condition. Some cities require developers to apply HA5 within one year of initial construction.
Anticipated Date (Design): 5.2019
Anticipated Date (Construction): 8.2019
Anticipated Date (Completion): 9.2019
Stillwater will benefit from this project by extending the life of residential asphalt streets.
Year Funded: FY2019
Funding Source: Transportation Sales Tax Fund
Project Budget:
Estimated at $300,000
Expenditure to date: $334,362
05.28.2019: Project documentation is under review.
09.28.2019: Project Complete
04.22.2019: City Council | Approval of FY19/20 Pavement Maintenance Program
Content Last Reviewed: 02.05.2021
![]() |