April 18, 2017: Right of Entry and Temporary Construction Easements have been acquired. The project will be advertised for bid beginning April 23, 2017. Construction is scheduled to begin in June.
July 26, 2016: Design is in progress and coordination with affected residents is being planned.
December 14, 2016: Right of Entry and Temporary Construction Easement requests were extended to affected property owners. Once coordination is complete, the next step will be to advertise for bids.
June 26, 2017: Bid opening occurred on June 21 and construction will begin in late July 2017.
August 10, 2017: Urban Contractors, LLC was awarded the contract and is currently working on the project.
September 5, 2017: The sewer point repairs are complete. Staff are inspecting the work and the Contractor is completing punch list items.
7.17.17 | SUA-17-20 | Bid Recommendation
Summerlin Addition
Village Court (click map to enlarge)
![]() |
(405) 372-0025 |
![]() |
723 S. Lewis St. Stillwater, OK 74074 |
|
New City Hall Hours: Mon-Thu: 7:30 am-5:30 pm Friday: 7:30-11:30 am |