Country Club Road & 37th Looping

Country Club Road & 37th Looping

Project Manager

Water Resources / Candy Staring

SUA Project No. 12WG17


What We're Doing

We are adding about 750 feet of new water line near the intersection of Country Club Road and 37th Street.


Project Benefits

This project eliminates two dead end lines in the southwest part of Stillwater. This increase in water circulation will improve water quality and increase reliability for the area.


Latest Project UpdateLatest Project Update

July 26, 2016: The notice to proceed for the contractor, Patriot Construction Services, was issued for an Aug. 1 construction start date.


Project Timeline

April 26, 2016: Design for this project is complete.  


Image:

(Click map to enlarge)

Design for Country Club Water Looping map