Placed 8 yards of concrete at two different locations
Repaired various street segments with hot patch and cold patch
Completed the asphalt patch on W. 26th Street
Picked up trash at Kameoka Trail and Boomer Lake
Painted the floor and walls at the south garage
Finished removing the concrete alley at Block 34
Pushed off rock and debris at the Stillwater Regional Airport
Removed concrete pillar at the hospital substation
Cleaned storm grates
Removed a tree off the gas line in the drainage channel at 824 Moore
Serviced equipment
Cleaned the sidewalk and the drainage channel between the sidewalk and parking lot at 821 N. Perkins Road
Bladed gravel parking lots
Filled the sinkhole in the 800 block of N. Jardot
Placed rip rap on the Elmwood drainage area
Replaced one signal head.
Responded to two trouble calls on intersections
Removed two older pieces of signal equipment
Installed radar detection at 6th and Fairgrounds
Completed two barricade setups
Made 20 signs
Installed 27 signs
Daily water demand: 4.675 MGAL
Set 4 new water meters
Inspected 36 fire hydrants
Repaired 3 water leaks
Installed 6 customer side valves
Performed 28 water quality flushes
Performed 196 City locates of water/sewer lines
Performed 8 rural locates of water lines
Turned on 1 meter
Shut off 10 meters
Checked for 3 potential water leaks
Completed 5 hydrant flow tests
Changed out 2 water meters
Checked 2 “no water” complaints
42 manhole inspected (acoustic inspection)
Raised manhole #4385 at 5921 Deer Creek
Rodded 7235 feet of sewer line (cleaned with high-pressure water)
Root cut from 1979 feet of sewer main
13 Manhole inspections
Cleared sewer easement from manhole #3382 to Manhole #3383 at 505 west 8th
Point repair and yard restoration at 811 S Knoblock (sewer main repair)
Treated 4.570 million gallons of drinking water each day
Set 3 new water meters
Inspected 19 hydrants
Repaired 1 water leak
Flushed 20 location points in the water distribution system
Performed 156 locates of city water/sewer lines
Performed 5 rural locates of water lines
Turned on 2 meters and shut off 5 meters
Checked for water leaks for 4 customers
Inspected 31 manholes
Cleaned and flushed 10,865 feet of sewer line
Cleared roots from 700 feet of sewer line
Made 11 signs and installed 14 signs.
Worked 1 snow day by clearing snow and ice along key streets and public buildings.
Concrete work at 3 locations: Southern Woods Park; 3rd and Hester; Block 34
Painted 2 locations: Preparing for the opening of the Stillwater Swimming Pool and removing graffiti at the drainage ditch behind Lowes.
Checked 50 drainage grates for obstructions.
Completed preventative maintenance on 1 signal
Repaired 2 traffic signals that were in flash mode
Installed 8 street signs at intersections
Completed 600 feet of striping